UFB1 April 2016 – April 2019

Location: North Shore

Scope: This project entailed the installation of:

  • Drilling and thrusting continuous duct, and ribbonets, 3813km
  • Trenching 4091Km
  • Hauling and proving ribbonet/micronet duct 7274Km
  • 52 Manholes
  • Aerial spanning 87301Km
  • Reinstatement, concrete and roadway 592m2
  • Testing, micronet/ribbonet 940
  • Blowing Fibre 8977KM
  • Splicing, lay up fibres in control Joint/ABFFP/AFAT/ Exchange
  • Traffic Management, L2 roadways, 53 Days

Achievements:

  • Move ZTK operations onto the North Shore after successful negotiations with Client.
  • Directional Drill Team No untility services strikes 100%.
  • Chours conducted multiple quility audits with positive outcomes.
  • Managing Projects while minimising impact to local residents through traffic management and working with the local community.
  • Installing total end to end Telecommunications infrastructure in the North Shore.
  • Meet the required productivity targets and deadlines.
  • Working multiple sites logistically challanging. This required intense traffic management in which Auckland Transport conducted multiple audits with very positive feedback.
  • Client Telco: North Shore Exchange
  • Date April 1, 2019
  • Tags Concrete repair and restoration, Fibre ducting installation, Horizontal directional drilling, Traffic and pedestrian management, Underground communications installation, Underground utilities installation